Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: DP14-0005
Permit Details
Apply Date:
01/07/2014
Applicant:
Description:
SITE/GRADING - GROUP HOME
Permit Reviews
Permit Number - DP14-0005
Permit Status: Complete
Permit Description: SITE/GRADING - GROUP HOME
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/07/2014 | DEV PKG - OK TO SUBMIT | 02/03/2014 | COMPLETED |
01/07/2014 | SITE and/or GRADING | 02/05/2014 | COMPLETED |
06/26/2014 | RESUB - SITE/GRADING ALL | 08/28/2014 | COMPLETED |
07/24/2015 | REVISION - SITE | 07/31/2015 | COMPLETED |
08/28/2014 | RESUB - SITE/GRADING ALL | 09/25/2014 | COMPLETED |
09/25/2014 | RESUB - SITE and/or GRADING | 09/29/2014 | COMPLETED |
09/29/2014 | RESUB - SITE and/or GRADING | 10/03/2014 | COMPLETED |
Outstanding Activity Conditions
Permit Number - DP14-0005
Permit Status: Complete
Permit Description: SITE/GRADING - GROUP HOME
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/10/2014 | AN APPROVED FIRE SPRINKLER SYSTEM AND FIRE ALARM SYSTEM IS REQUIRED FOR THIS GROUP I OCCUPANCY. UTILITY PLANS WILL NEED TO INDICATE FIRE SPRINKLER UNDERGROUND |
Completed Inspections
Permit Status: Complete
Permit Number: DP14-0005
Permit Description: SITE/GRADING - GROUP HOME
Total Completed Inspections - 7
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/10/2015 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 08/10/2015; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
08/10/2015 | ENGR Engineering Final | Passed | {Activity date: 08/10/2015; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
08/10/2015 | SITE - Stormwater Follow-up | Passed | {Activity date: 08/10/2015; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 06/01/2015; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NO CONCERNS AT THIS TIME, REMINDED THE CREWS TO WATCH THE DUST CONTROL AND TO PREVENT TRACKOUT ONTO MOUNTAIN.} ; {Activity date: 05/21/2015; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NO CONCERNS AT THIS TIME, HAVE REMINDED THE CREWS TO MAINTAIN THERE SITE SO THAT WE DO NOT HAVE ANY TRACKOUT} | |
08/10/2015 | ENGR Grading Final | Passed | {Activity date: 08/10/2015; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 05/08/2015; Status: Not ready for Inspection; Inspector: DROBERTS; Comment: Entered by DROBERT5 - SITE IS NOT READY AT THIS TIME FOR APPROVAL, BUT THERE MAY BE SOME CONFLICT WITH MOUNTAIN, NEW SIDEWALK, DRIVEWAYS, TRASH ENCLOSURES, AND EXISTING MAILBOXES.} | |
08/10/2015 | SITE - Stormwater Final Inspection | Passed | {Activity date: 08/10/2015; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
08/10/2015 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 08/10/2015; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
08/10/2015 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 08/10/2015; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } |