Permit Details

Status:
Complete
Type:
Development Package
Address:
6255 S 12TH AV
Address NEW:
6255 S 12TH AV
Apply Date:
08/27/2013
Applicant:
Description:
SITE/GRADING

Permit Reviews

Permit Number - DP13-0166
Permit Status: Complete
Permit Description: SITE/GRADING
Start Date Submittal Complete Date Status  
02/14/2014 REVISION - - 1ST 02/24/2014 COMPLETED Review Details
08/24/2015 REVISION - GRADING 09/24/2015 COMPLETED Review Details
08/26/2015 SITE and/or GRADING 08/26/2015 COMPLETED Review Details
08/27/2013 DEV PKG - OK TO SUBMIT 08/27/2013 COMPLETED Review Details
08/27/2013 SITE and/or GRADING 12/03/2013 COMPLETED Review Details
09/24/2015 REVISION - GRADING 09/28/2015 COMPLETED Review Details
09/28/2015 REVISION - GRADING 11/12/2015 COMPLETED Review Details
11/21/2013 RESUB - SITE and/or GRADING 12/03/2013 COMPLETED Review Details
12/03/2013 RESUB - SITE/GRADING ALL 12/03/2013 COMPLETED Review Details
12/03/2013 RESUB - SITE/GRADING ALL 01/23/2014 COMPLETED Review Details

Conditions

Permit Number - DP13-0166
Permit Status: Complete
Permit Description: SITE/GRADING
Date Description Comments
12/03/2013 At least one curb opening from the parking area to the landscape area must be provided within 20 feet of the driveway to Santa Maria Street. The opening must also be shown on a revised grading DP before the project is complete.
12/03/2013 A complete drainage report meeting the format requirements of the the Drainage Manual must be submitted and approved before the final grading inspection is approved.

Completed Inspections

Permit Status: Complete
Permit Number: DP13-0166
Permit Description: SITE/GRADING
Total Completed Inspections - 7
Date Description Inspector Results Comments
07/10/2014 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 07/10/2014; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO SWPPP PLAN NEEDED PER LOREN MAKUS.} ; {Activity date: 07/09/2014; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 05/05/2014; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - COMPLET NOTES FROM 1-28-2014} ; {Activity date: 01/28/2014; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - PROVIDE APPROVED SWPPP PLAN AND NOI FOR THIS ACTIVITY.} ; {Activity date: 01/27/2014; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - CHECKING FOR SWPPP FOR SITE}
11/26/2014 SITE - Stormwater Final Inspection Passed {Activity date: 11/26/2014; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 09/25/2001; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - THIS SITE WILL BE INSPECTED BY RON LE DONNE WHEN HE RETURNS ON 9/30/2014}
11/26/2014 SITE - Stormwater Setup and Controls Passed {Activity date: 11/26/2014; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
06/23/2015 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 06/23/2015; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 02/25/2015; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 11/26/2014; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
07/23/2015 SITE - Stormwater Follow-up Passed {Activity date: 07/23/2015; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
11/19/2015 ENGR Engineering Final Passed {Activity date: 11/19/2015; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 07/23/2015; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - COMPLET NOTES FROM LAST INSPECTION.} ; {Activity date: 06/23/2015; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - PROVIDE AS-BUILTS FOR ALL CHANGES TO GRADING AND DRAINAGE.} ; {Activity date: 11/26/2014; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 09/25/2014; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - THIS SITE WILL BE INSPECTED BY RON LE DONNE WHEN HE RETURNS ON 9/30/2014}
11/19/2015 ENGR Grading Final Passed {Activity date: 11/19/2015; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 07/23/2015; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - AS-BUILTS NEEDED PER LOREN MAKUS.} ; {Activity date: 07/23/2015; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 06/23/2015; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }

Documents

File Name Document Type  
001_C.TIF GRADING PLANS VIEW
002_SHEET 1.TIF GRADING PLANS VIEW
003_SHEET 2.TIF GRADING PLANS VIEW
004_SHEET 3.0.TIF GRADING PLANS VIEW
005_SHEET 3.1.TIF GRADING PLANS VIEW
006_L-1.TIF GRADING PLANS VIEW
007_L-2.TIF GRADING PLANS VIEW
008_L-3.TIF GRADING PLANS VIEW
None DOCUMENTS VIEW