Permit Details

Status:
Complete
Type:
Development Package
Address:
909 E 22ND ST
Apply Date:
04/13/2012
Applicant:
Description:
SITE/GRADING - CAR WASH

Permit Reviews

Permit Number - DP12-0048
Permit Status: Complete
Permit Description: SITE/GRADING - CAR WASH
Start Date Submittal Complete Date Status  
02/07/2013 RESUB - SITE and/or GRADING 03/01/2013 COMPLETED Review Details
03/01/2013 RESUB - SITE and/or GRADING 05/23/2013 COMPLETED Review Details
04/13/2012 DEV PKG - OK TO SUBMIT (SITE) 04/13/2012 COMPLETED Review Details
04/13/2012 SITE and/or GRADING 02/07/2013 COMPLETED Review Details
05/23/2013 REVISION - SITE 06/05/2013 COMPLETED Review Details
11/14/2013 REVISION - SITE 11/15/2013 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - DP12-0048
Permit Status: Complete
Permit Description: SITE/GRADING - CAR WASH
Total Outstanding Activity Conditions - 2
Date Name
05/08/2013 SPECIAL INSPECTION IS REQ'D FOR AN ELEVATION CERTIFICATE.THE ELEVATION OF THE FORMED PRE-SLAB MUST BE SUBMITTED ON AN ELEVATION CERTIFICATE AND SEALED BY A REGISTERED LAND SURVEYOR. FAX OR EMAIL ELEVATION CERTIFICATE TO: ATTENTION LOREN MAKUS. FAX: 879-8010, EMAIL: LOREN.MAKUS@TUCSONAZ.GOV. THIS CONDITION APPLIES TO INSPECTION 1015 AND SHOULD NOT BE SCHEDULED UNTIL THE ELEVATION CERTIFICATE AND THE CONDITION HAVE BEEN APPROVED. LOREN'S IS 837-4927.
05/08/2013 FINAL ELEVATION CERTIFICATE REQUIRED: AN ORIGINAL FINAL ELEVATION CERTIFICATE SEALED BY A REGISTERED LAND SURVEYOR IS REQ'D. MAIL ELEVATION CERTIFICATE TO: CITY OF TUCSON, PLANNING & DEVELOPMENT SERVICES DEPT, ATTN: LOREN MAKUS, P.O. BOX 27210, TUCSON, AZ 85726-7210 OR DELIVER IT TO THE 1ST FL NORTH SIDE OF 201 N. STONE AVE. THIS CONDITION APPLIES TO ALL FINAL INSPECTIONS (1090, 2090, 3090, 4090) AND SHOULD NOT BE SCHEDULED UNTIL THE ELEVATION CERTIFICATE AND THE CONDITION HAVE BEEN APPROVED. LOREN'S IS 837-4927.

Completed Inspections

Permit Status: Complete
Permit Number: DP12-0048
Permit Description: SITE/GRADING - CAR WASH
Total Completed Inspections - 11
Date Description Inspector Results Comments
07/24/2013 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 07/24/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 07/19/2013; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - PRE-CON WITH DON GC. DROPED OFF PRE-CON PACKET.}
08/14/2013 COT - ENGR - Site - Assurance Release Passed {Activity date: 08/14/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/28/2013 SITE - SWPPP Correction Notice Passed {Activity date: 10/28/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 08/23/2013; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - CONCRETE WASHOUT NOT INSTALLED.} ; {Activity date: 08/21/2013; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - GOT WITH GC TO INSTALL CONCRETE WASHOUT.}
10/28/2013 SITE - Stormwater Follow-up Passed {Activity date: 10/28/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 09/13/2013; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - GOT WITH GC ABOUT CONCRETE WASH OUT .} ; {Activity date: 08/14/2013; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO TACK OUT AT THIS TIME.}
10/28/2013 SITE - SWPPP Violation Notice Passed {Activity date: 10/28/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/28/2013 SITE - Stormwater Final Inspection Passed {Activity date: 10/28/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/28/2013 SITE - Stormwater Setup and Controls Passed {Activity date: 10/28/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
11/19/2013 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 11/19/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
11/22/2013 ENGR Engineering Final Passed {Activity date: 11/22/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 11/19/2013; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
11/22/2013 ENGR Grading Final Passed {Activity date: 11/22/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/28/2014 RSBU - Building Final Passed {Activity date: 10/28/2014; Status: Approved; Inspector: kmedina; Comment: Entered by KMEDINA1 - }

Documents

File Name Document Type  
001_MASTER COVER SHEET_1 OF 12.TIF DEVELOPMENT PACKAGE VIEW
002_SITE_2 OF 12.TIF DEVELOPMENT PACKAGE VIEW
003_DEMOLITION_3 OF 12.TIF DEVELOPMENT PACKAGE VIEW
004_GRADING/PAVING/DRAINAGE_4 OF 12.TIF DEVELOPMENT PACKAGE VIEW
005_NOTES/DETAILS_5 OF 12.TIF DEVELOPMENT PACKAGE VIEW
006_PRIVATE UTILITY_6 OF 12.TIF DEVELOPMENT PACKAGE VIEW
007_HORIZONTAL CONTROL_7 OF 12.TIF DEVELOPMENT PACKAGE VIEW
008_LANDSCAPE/RAIN WATER HARVESTING_8 OF 12.TIF DEVELOPMENT PACKAGE VIEW
009_LANDSCAPE/RAIN WATER HARVESTING_9 OF 12.TIF DEVELOPMENT PACKAGE VIEW
010_LANDSCAPE/RAIN WATER HARVESTING_10 OF 12.TIF DEVELOPMENT PACKAGE VIEW
011_LANDSCAPE/RAIN WATER HARVESTING_11 OF 12.TIF DEVELOPMENT PACKAGE VIEW
012_LANDSCAPE/RAIN WATER HARVESTING_12 OF 12.TIF DEVELOPMENT PACKAGE VIEW