Permit: DP11-0002
Permit Details
Apply Date:
11/03/2011
Applicant:
Lisa Bowers
Description:
SITE/GRADING FOR NEW PARKING LOT
Permit Reviews
Permit Number - DP11-0002
Permit Status: Complete
Permit Description: SITE/GRADING FOR NEW PARKING LOT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/06/2012 | RESUBMITTAL - SITE | 01/12/2012 | COMPLETED |
08/23/2012 | REVISION - SITE | 08/23/2012 | COMPLETED |
08/23/2012 | REVISION - SITE | 08/27/2012 | COMPLETED |
08/27/2012 | REVISION - SITE | 09/19/2012 | COMPLETED |
09/19/2012 | REVISION - SITE | 09/27/2012 | COMPLETED |
11/08/2011 | DEVELOPMENT PKG | 12/23/2011 | COMPLETED |
12/23/2011 | RESUBMITTAL - SITE | 01/06/2012 | COMPLETED |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP11-0002
Permite Description: SITE/GRADING FOR NEW PARKING LOT
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/09/2012 | PDSD Site/Engineering Division - Landscaping | N/A | Complete (Recurring) | {Activity date: 08/09/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 08/09/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 05/02/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WORKING ON LANDSCAPING ON EAST AND WEST SIDE OF BUILDING.} ; {Activity date: 04/03/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - PER HIGH LIGHTS ON PAGE 7OF12. PROVDE AP PLANS FOR ALL CHANGES TO NPPO.} |
Completed Inspections
Permit Status: Complete
Permit Number: DP11-0002
Permit Description: SITE/GRADING FOR NEW PARKING LOT
Total Completed Inspections - 6
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/10/2012 | ENGR Grading Final | Passed | {Activity date: 05/10/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 05/04/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - GOT WITH CONTRACTOR TO PROVIDE STABILIZATION FOR DISTURBED AREA OFF SITE.} ; {Activity date: 04/26/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - GRADING ON WEST SIDE OF PARKING AREA.} ; {Activity date: 04/13/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WORKING ON CURBING ON WEST SIDE PARKING AREA.} ; {Activity date: 04/10/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WORKING ON GRADING NO TRACK OUT AT THIS TIME.} ; {Activity date: 04/06/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO TRACK OUT AT THIS TIME.} ; {Activity date: 04/05/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - ROCK HAS BEEN INSTALLED AT GATE.} ; {Activity date: 03/29/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WORKING ON EAST SIDE PARKING AREA.} ; {Activity date: 03/26/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - PAVING ON EAST SIDE OF PARKING AREA .} ; {Activity date: 03/23/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - STARTING TO PAVE ON SOUTH SIDE OF PARKING AREA.} ; {Activity date: 03/20/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - RAIN DAY NO GRADING WORK AT THIS TIME .CONTRACTOR NOT ON SITE.} ; {Activity date: 03/19/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WORKING ON CURBS AND GRADING.} ; {Activity date: 03/16/2012; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 03/14/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WORKING ON GRADING IN NEW PARKING AREA .} ; {Activity date: 03/01/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - ROUGH GRADING AT THIS TIME.} ; {Activity date: 02/27/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - PROVIDE APPROVEL FOR CHANGE TO LANDSCAPING PLANS.} ; {Activity date: 02/14/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO ACTIVITY AT THIS TIME.} | |
10/17/2012 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 10/17/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by CAGUILA1 - } ; {Activity date: 08/09/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 05/10/2012; Status: Denied; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 05/09/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WORKING ON LANDSCAPING ON WEST SIDE .} ; {Activity date: 03/15/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 02/08/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO ACTIVITY AT THIS TIME.} | |
10/17/2012 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 10/17/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by CAGUILA1 - } ; {Activity date: 08/09/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 05/10/2012; Status: Denied; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 02/22/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WORKING ON INSTALLING PROTECTION FOR NPPO PIP.} | |
10/17/2012 | ENGR Engineering Final | Passed | {Activity date: 10/17/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by CAGUILA1 - } ; {Activity date: 08/30/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - GOT WITH JASON GREEN WENT OVER AS-BUILTS. WENT TO SITE TO CHECK PARKING AREA . NOT PER AP PLANS.} ; {Activity date: 08/28/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - GOT WITH JASON GREEN ON AS-BUILTS THAT ARE NOT COMPLET.} ; {Activity date: 08/22/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO ACTIVITY AT THIS TIME.} ; {Activity date: 07/24/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WORKING ON CURBING IN RIGHT-A -WAY ONLY. NO GRADING ACTIVITY.} ; {Activity date: 07/11/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CHANGE FROM LAST INSPECTION.} ; {Activity date: 05/10/2012; Status: Denied; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - COMPLET ALL AS-BUITS FOR ALL CHANGES TO PARKING AND LANDSCAPING . PROVVIDE STABILIZATION PER COMMENTS ON 5-4-2012. POVIDE CERT LETTERS FOR GRADING AND DRAINAGE.} ; {Activity date: 04/26/2012; Status: Denied; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
10/17/2012 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 10/17/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by CAGUILA1 - } ; {Activity date: 02/01/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO GRADING ACTIVITY AT THIS TIME.} ; {Activity date: 01/18/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - DAVE COLLINS- BRYAN JONSON AT PRE-CON} | |
04/19/2017 | RSBU - Building Final | Passed | {Activity date: 04/19/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } |