Status:
Complete
Type:
Development Package
Address:
1150 W DREXEL RD
Apply Date:
11/03/2011
Applicant:
Lisa Bowers
Description:
SITE/GRADING FOR NEW PARKING LOT

Permit Reviews

Permit Number - DP11-0002
Permit Status: Complete
Permit Description: SITE/GRADING FOR NEW PARKING LOT
Start Date Submittal Complete Date Status  
01/06/2012 RESUBMITTAL - SITE 01/12/2012 COMPLETED Review Details
08/23/2012 REVISION - SITE 08/23/2012 COMPLETED Review Details
08/23/2012 REVISION - SITE 08/27/2012 COMPLETED Review Details
08/27/2012 REVISION - SITE 09/19/2012 COMPLETED Review Details
09/19/2012 REVISION - SITE 09/27/2012 COMPLETED Review Details
11/08/2011 DEVELOPMENT PKG 12/23/2011 COMPLETED Review Details
12/23/2011 RESUBMITTAL - SITE 01/06/2012 COMPLETED Review Details

Outstanding Inspections

Permit Status: Complete
Permit Number: DP11-0002
Permite Description: SITE/GRADING FOR NEW PARKING LOT
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
08/09/2012 PDSD Site/Engineering Division - Landscaping N/A Complete (Recurring) {Activity date: 08/09/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 08/09/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 05/02/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WORKING ON LANDSCAPING ON EAST AND WEST SIDE OF BUILDING.} ; {Activity date: 04/03/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - PER HIGH LIGHTS ON PAGE 7OF12. PROVDE AP PLANS FOR ALL CHANGES TO NPPO.}

Completed Inspections

Permit Status: Complete
Permit Number: DP11-0002
Permit Description: SITE/GRADING FOR NEW PARKING LOT
Total Completed Inspections - 6
Date Description Inspector Results Comments
05/10/2012 ENGR Grading Final Passed {Activity date: 05/10/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 05/04/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - GOT WITH CONTRACTOR TO PROVIDE STABILIZATION FOR DISTURBED AREA OFF SITE.} ; {Activity date: 04/26/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - GRADING ON WEST SIDE OF PARKING AREA.} ; {Activity date: 04/13/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WORKING ON CURBING ON WEST SIDE PARKING AREA.} ; {Activity date: 04/10/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WORKING ON GRADING NO TRACK OUT AT THIS TIME.} ; {Activity date: 04/06/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO TRACK OUT AT THIS TIME.} ; {Activity date: 04/05/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - ROCK HAS BEEN INSTALLED AT GATE.} ; {Activity date: 03/29/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WORKING ON EAST SIDE PARKING AREA.} ; {Activity date: 03/26/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - PAVING ON EAST SIDE OF PARKING AREA .} ; {Activity date: 03/23/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - STARTING TO PAVE ON SOUTH SIDE OF PARKING AREA.} ; {Activity date: 03/20/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - RAIN DAY NO GRADING WORK AT THIS TIME .CONTRACTOR NOT ON SITE.} ; {Activity date: 03/19/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WORKING ON CURBS AND GRADING.} ; {Activity date: 03/16/2012; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 03/14/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WORKING ON GRADING IN NEW PARKING AREA .} ; {Activity date: 03/01/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - ROUGH GRADING AT THIS TIME.} ; {Activity date: 02/27/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - PROVIDE APPROVEL FOR CHANGE TO LANDSCAPING PLANS.} ; {Activity date: 02/14/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO ACTIVITY AT THIS TIME.}
10/17/2012 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 10/17/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by CAGUILA1 - } ; {Activity date: 08/09/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 05/10/2012; Status: Denied; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 05/09/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WORKING ON LANDSCAPING ON WEST SIDE .} ; {Activity date: 03/15/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 02/08/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO ACTIVITY AT THIS TIME.}
10/17/2012 PDSD Site/Engineering Division - NPPO Passed {Activity date: 10/17/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by CAGUILA1 - } ; {Activity date: 08/09/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 05/10/2012; Status: Denied; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 02/22/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WORKING ON INSTALLING PROTECTION FOR NPPO PIP.}
10/17/2012 ENGR Engineering Final Passed {Activity date: 10/17/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by CAGUILA1 - } ; {Activity date: 08/30/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - GOT WITH JASON GREEN WENT OVER AS-BUILTS. WENT TO SITE TO CHECK PARKING AREA . NOT PER AP PLANS.} ; {Activity date: 08/28/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - GOT WITH JASON GREEN ON AS-BUILTS THAT ARE NOT COMPLET.} ; {Activity date: 08/22/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO ACTIVITY AT THIS TIME.} ; {Activity date: 07/24/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WORKING ON CURBING IN RIGHT-A -WAY ONLY. NO GRADING ACTIVITY.} ; {Activity date: 07/11/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CHANGE FROM LAST INSPECTION.} ; {Activity date: 05/10/2012; Status: Denied; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - COMPLET ALL AS-BUITS FOR ALL CHANGES TO PARKING AND LANDSCAPING . PROVVIDE STABILIZATION PER COMMENTS ON 5-4-2012. POVIDE CERT LETTERS FOR GRADING AND DRAINAGE.} ; {Activity date: 04/26/2012; Status: Denied; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/17/2012 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 10/17/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by CAGUILA1 - } ; {Activity date: 02/01/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO GRADING ACTIVITY AT THIS TIME.} ; {Activity date: 01/18/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - DAVE COLLINS- BRYAN JONSON AT PRE-CON}
04/19/2017 RSBU - Building Final Passed {Activity date: 04/19/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }

Documents

File Name Document Type  
None DOCUMENTS VIEW
PERFORMANCE BOND 2012_01_11.PDF DOCUMENTS VIEW
None DOCUMENTS VIEW
DP11-0002 RELEASE LETTER.PDF DOCUMENTS VIEW
001_REF SITE_ 1 OF 12.TIF DEVPLANS VIEW
002_SITE_ 2 OF 12.TIF DEVPLANS VIEW
003_PAVING & GRADING_3 OF 12.TIF DEVPLANS VIEW
004_PAVING & GRADING_4 OF 12.TIF DEVPLANS VIEW
005_PAVING & GRADING_5 OF 12.TIF DEVPLANS VIEW
006_PAVING & GRADING_6 OF 12.TIF DEVPLANS VIEW
007_LANDSCAPE_7 OF 12.TIF DEVPLANS VIEW
008_IRRIGATION_8 OF 12.TIF DEVPLANS VIEW
009_PLANTING & IRRIGATION_9 OF 12.TIF DEVPLANS VIEW
010_NPPP_10 OF 12.TIF DEVPLANS VIEW
011_NATIVE PLANT INVENTORY_11 OF 12.TIF DEVPLANS VIEW