Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Parcel Search
 
Parcel Attributes
Parcel13113223C
JurisdictionTucson, Pima County
City of Tucson ZoningO-3
Tucson WardWard 4
Tucson Registered NeighborhoodCorbett
Major Street & Route

Gateway Route

Pima County Data Assessor, Recorder, Treasurer, ...
Parcel Map Map
Address
Parcel Attributes Issue?

Annexations & Original City Zoning (OCZ)

Date - 11/21/2026 12:56 a.m.
Total Number Of OZC Plans - (1)
Plan Description Annexation Ordinance Effective Date OCZ Ordinance
C9-59-19 North To Roger Rd. And East To Kolb Rd. 1895 04/26/1959 1957

Permits

Parcel Number - 13113223C
Date - 11/21/2026 12:56 a.m.
Total Number Of Permits - (1)
Permit Permit Status Entered Date Expired Date Unit Type Description
TR-FBR-1126-00040 Inspections 11/16/2026 01/16/2027 Fiber Permit #26-0329 Tucson - Zone 234.1 Total Estimated Linear Feet (Excavation/Bore): 4,048 feet Permit SOW: Scope of Work is S Rook Ave west to S Del Valle and between E Golf Link Rd north to E 33rd St Ideatek is Expanding Fiber Optic Cable Network in Tucson. This fiber be placed in Tucson Road Right of Way. Fiber will be buried min 36" deep in ROW. Work will be done with Directional Bore Machines by placing 1.25"-2" Sch 40 Orange Duct. Backbone fiber Count ranges from 48ct up 96ct and pulled through duct. Vault and service pedestals to be placed along route to serve as splicing points. PLEASE SEE ATTACHED APPROVED SITE PLANS AND TCP FOR BETTER DETAILS. Ideatek Project Manager Contact: Ron Willey 816-661-7440 rwilley@ideatek.com Contractor Contact Infor: Peter Lela 602-799-2366 Peter@veltorunderground.com

Plans

Parcel Number - 13113223C
Date - 11/21/2026 12:56 a.m.
Total Number Of Plans - 1
Plan Number Plan Status Application Date Expired Date Unit Type Description
TR-FTTP-1026-00015 Approved 10/12/2026 04/12/2027 Fiber Plan Review #26-0329 Tucson - Zone 234 Total Estimated Linear Feet (Excavation/Bore): 21,005 feet Serviceable Locations - 421 Project Scope & Overview Installation of new fiber-optic infrastructure within the City of Tucson public right-of-way (ROW) to support local telecommunications and high-speed broadband expansion. Construction activity includes underground conduit installation, vault/handhole placement, fiber placement, overhead pole attachment where applicable, and site restoration. Detailed Work Plan Underground Excavation & Installation Directional Boring (Trenchless): Placement of high-density polyethylene (HDPE) conduit via horizontal directional drilling (HDD) to minimize surface disruption. Open Trenching / Micro-Trenching: Excavation for conduit installation where directional boring is not feasible. All trenching and backfill will strictly adhere to City of Tucson Chapter 25 Code, Standard Details, and D.S. 3-03 Pavement Cut Requirements. City of Tucson Structures: Installation of flush-to-grade composite underground vaults and handholes at designated splice locations and lateral tie-ins. Aerial Operations (If Applicable) Attachment of fiber optic cable and strand to existing utility poles in accordance with signed pole attachment agreements and City requirements. No remaining on abandoned poles. City of Tucson Traffic Control & Safety Implementation of temporary traffic control, lane closures, or sidewalk detours in full compliance with the Manual on Uniform Traffic Control Devices (MUTCD), City Code Chapter 25, and approved City of Tucson Department of Transportation & Mobility (DTM) Barricade and Excavation Permits. City of Tucson Utility Coordination & Underground Safety Pre-construction utility locates will be coordinated through Arizona 811. Work occurring near Tucson Water infrastructure will maintain required horizontal clearances and comply with Tucson Water Distribution Design guidelines. Restoration & Site Clean-Up All impacted asphalt, concrete, sidewalks, curbs, ADA ramps, and landscaping will be restored to original or better condition per City of Tucson standard details. Asphalt patches will meet City pavement cut restoration standards. Quantities & Location Details Number of Vaults/Handholes: Service Pedestal - 103 Vault 44 24" x 36" - 19 15" x 24" - 24 10” Flower Pot - 1 Project Location/Limits: E Golf Link Rd north to E 29th St and Between S Wilmot Rd West to S Sahuara Ave. This plan consists of 5 permit sections = 5 ROW Fiber permits will be applied for upon approval of this plan. PLEASE SEE ATTACHED SITE PLANS AND TCP FOR BETTER DETAILS