Inspection Status: Completed
Inspection History: COT - FCOD - Fire Re-inspection
Case Number - _FAF6ADBE9E012
Inspection Description - COT - FCOD - Fire Re-inspection
Inspection Status - Completed
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/12/2020 | COT - FCOD - Fire Re-inspection | Completed | ||
| 11/09/2020 | COT - FCOD - Fire Re-inspection | Completed | JH 11/9/20 spoke with Robert from Central Alarm. Fire alarm panel and remining sytem are back in service and working properly. | |
| 05/03/2017 | COT - FCOD - Fire Re-inspection | Completed | Hotel Alarm give 2 yr extension | |
| 05/20/2015 | COT - FCOD - Fire Re-inspection | Completed | JH 5/20/15 appeal turned into TFD. Ken B. will be handling appeal. | |
| 04/23/2015 | COT - FCOD - Fire Re-inspection | Completed | JH 3-4-15 Kamish is talking with OEM about wireless alarm system. Extending re-inspection out 2 weeks from today. New re-inspect will be March 15, 2015. Contract needs to be signed by March 15. Kamish has been notified of new re-inspection date. JH 3-17-15 OEM is backed up on proposals. Company needs more time. Will push out 2 more weeks. JH 4-1-15 George from OEM is still working on bids for multiple hotels. Kamish's cell # 603-1248 JH 4-14-15 Spoke with Kamish. He stated fire alarm proposal from OEM was financially not possible. I gave him Ken Brouilette's number. He would like to speak with Ken. He also stated he is meeting with the owner of the motel and a few others to discuss fire alarm. JH 4-23-15 See pre-cite |
|
| 02/26/2015 | COT - FCOD - Fire Re-inspection | Completed | JH 2-26-15 Hotel called 3 companies. Only 1 came out and gave a bid. OEM firealarms is working on a bid for this hotel and other hotels owned by the same owner. OEM can give a better deal financially to all the hotels if they do a package deal. Therefore, hotel will have more time to allow OEM to finish bid. | |
| 01/12/2015 | COT - FCOD - Fire Re-inspection | Completed | JH 3-4-15 Kamish is talking with OEM about wireless alarm system. Extending re-inspection out 2 weeks from today. New re-inspect will be March 15, 2015. Contract needs to be signed by March 15. Kamish has been notified of new re-inspection date. JH 3-17-15 OEM is backed up on proposals. Company needs more time. Will push out 2 more weeks. JH 4-1-15 George from OEM is still working on bids for multiple hotels. Kamish's cell # 603-1248 JH 4-14-15 Spoke with Kamish. He stated fire alarm proposal from OEM was financially not possible. I gave him Ken Brouilette's number. He would like to speak with Ken. He also stated he is meeting with the owner of the motel and a few others to discuss fire alarm. |
|
| 04/23/2015 | COT - FCOD - Fire Re-inspection | Completed | JH 4-13-15 See attachment. Kamish(rep) did not want to sign paperwork. He states he will e-mail paperwork when owner signs it. | |
| 12/03/2014 | COT - FCOD - Fire Re-inspection | Completed |