Inspection Status: In Field Accepted
Inspection History: TWPE Summary review of Daily Field Inspections
| Date |
Description |
Inspector |
Results |
Comments |
| 05/12/2026 |
TWPE Summary review of Daily Field Inspections |
|
In Field Accepted |
HB installed 4” gate valve at station 12+61.53. They used 3 way connectors and ran new tracer wire. |
| 05/22/2026 |
TWPE Summary review of Daily Field Inspections |
|
In Field Accepted |
Tricon installed 3” meter assembly and laid brick to enclose area. They painted assembly. |
| 05/28/2026 |
TWPE Summary review of Daily Field Inspections |
|
In Field Accepted |
Tricon completed block wall around meter assembly. Concrete valve collars were completed as well. |
| 06/03/2026 |
TWPE Summary review of Daily Field Inspections |
|
Failed |
refer to notes on photo attachment. |
| 06/04/2026 |
TWPE Summary review of Daily Field Inspections |
|
In Field Accepted |
GC Jamie Johnson had his crew redo the concrete collar at station 10+00.0. I met w Aaron to review items on the final punch list. Once the sidewalk is poured I can complete my inspection for the final valve riser. Once that complete, I will release the 1” irrigation meter. |
| 06/09/2026 |
TWPE Summary review of Daily Field Inspections |
|
Canceled |
|