Inspection History Details
Inspection Status: In Field Accepted
Inspection History: TWPE Summary review of Daily Field Inspections
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/06/2026 | TWPE Summary review of Daily Field Inspections | In Field Accepted | ||
| 06/11/2026 | TWPE Summary review of Daily Field Inspections | In Field Accepted | There will be water work inspection needed today | |
| 06/23/2026 | TWPE Summary review of Daily Field Inspections | In Field Accepted | ||
| 07/02/2026 | TWPE Summary review of Daily Field Inspections | In Field Accepted | I met with Fernando Contreras this morning. He advised me that he will have a crew working on valve adjustments and concrete collars. Fernando also mentioned he will quit at 11:00 am today. | |
| 07/08/2026 | TWPE Summary review of Daily Field Inspections | In Field Accepted | ||
| 07/22/2026 | TWPE Summary review of Daily Field Inspections | In Field Accepted | Arles will continue on new main installment. The crew will start on W Valencia Rd. at approx sta 26+00 and work WB. They installed 80 LF stopping at sta 25+20. The crew also installed one WS. Robbie will have his crew working on WS. Addresses; 758, 750, 766, 742 W Calle de Casas Lindas Mario will also continue to work on WS. addresses completed; 910, 902, 911, 903 W Calle de Casas Lindas |
|
| 07/29/2026 | TWPE Summary review of Daily Field Inspections | In Field Accepted | I met with Fernando this morning, the majority of the crew will be working on WS, Mario’s crew, Robbie’s crew, and Arles crew will be on WS. Hunter will have two laborers working on valve adjustments and concrete collars in the intersection of Calle de Casas Lindas and S Santa Clara Ave. | |
| TWPE Summary review of Daily Field Inspections | Scheduled |