Inspection History Details
Inspection Status: In Field Accepted
Inspection History: TWPE Daily Field Inspection
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/29/2026 | TWPE Daily Field Inspection | In Field Accepted | I met with supervisor Al. They started milling 35th and will begin excavation next week. I gave him my contact information. Their work hours are 6-2pm. | |
| 06/01/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon milled 35th avenue aid 1/3 of 36th ave. They will finish milling tomorrow. | |
| 06/02/2026 | TWPE Daily Field Inspection | In Field Accepted | TRICON continued milling 36th st. | |
| 06/08/2026 | TWPE Daily Field Inspection | In Field Accepted | I reviewed submittals and confirmed Tricon broke off all megalugs. They sleeved all DIP and assembled all gate valves, fire hydrants, Tee.’s and 9’s. Tri Con completed milling and began excavating. They laid pipe from station 29+23.77 to station 26+00. They used sweeper to clean street after excavation. |
|
| 06/09/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon trenched to station 24+50. Tee was installed at station 25.41. Branch and Fh will be installed at a later date. Tricon is processing dirt, using bury tape and compacting to spec. | |
| 06/10/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 06/11/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 06/15/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon got rained out and didn’t work today. | |
| 06/16/2026 | TWPE Daily Field Inspection | In Field Accepted | I can’t go back and edit or add to my notes. It says read only. Tee was installed at station 18+53 and laid pipe to station 18+00. They compacted tench to spec, used tracer wire. TOP was 5’2. |
|
| 06/17/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon install FH at station 25+41. They used restraints and installed sac cathode. They laid 8”DIP to station 13+50. All sewer laterals have 12” separation and sew wrapped. They’re backfilling with processed dirt and leaving the roadways clean. | |
| 06/18/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon laid pipe to station 13+00 and installed Fh at station 18+53. They compacted in 1’ lifts. | |
| 06/19/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon laid pipe to station 12+00. They finished milling roadway on 36th st. They backfilled with processed dirt. foreman Al stated they have a sweeper crew that comes out every friday. | |
| 06/22/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon laid pipe to station 10+50. on 36th. I emailed Stephen Espinoza about relocating FH station 23+20.73 30ft south. Survey has current FH location install in the middle of a customers driveway. They laid pipe on 36th to station 29+02.53. FH was installed as well. |
|
| 06/23/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon completed two hot tap on 32nd street. They finished with temp patch. They laid pipe to station 28+00 on 36th street. They installed tee at station 22+73.99 |
|
| 06/24/2026 | TWPE Daily Field Inspection | In Field Accepted | Tw water maintenance located and exercised valves for mock shut down. They were pulled off due to emergency. I left voice mail w supervisor rocco depaulo. Tricon tapped two services on Sahuara and ran copper service and set meter boxes. They trenched and laid pipe to station 26+50 on 36th street and to the DVA on VanBuren. I placed order for 105 meter boxes at the east side stores for tri con to pick. I informed Tricon and sent them receipt. |
|
| 06/25/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon laid pipe and installed tee and FH at stations 25+41.00 and 22+73.99. | |
| 06/29/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon trenched and laid pipe to station 25+00.23. Tee and gate valves were installed. Trench was backfilled and compacted to spec. | |
| 07/01/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon installed 45 at station 10+66 and laid pipe to station 12+00. Trench was backfilled. | |
| 07/02/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon is working a short shift today to prevent ot. They potholed to prep for FH install at station 18+35. They swept roads and left a clean site. | |
| 07/09/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon laid 8” DIP to station 15+00. MOCK shutdown is scheduled tonight at 10pm. | |
| 07/10/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon laid pipe to station 17+00. | |
| 07/14/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon laid pipe to station to 17+50. They swept the roadway and prepped to install FH tomorrow. | |
| 07/15/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon laid pipe to station 18+00. they will install tee and FH tomorrow. | |
| 07/16/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon laid pipe and installed FH at station 18+35. | |
| 07/17/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon laid pipe to station 19+50. They located mainline that crosses road. | |
| 07/21/2026 | TWPE Daily Field Inspection | In Field Accepted | Tri con laid pipe to station 21+50. | |
| 07/22/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon laid pipe to station 23+00. | |
| 07/24/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon laid pipe to station 22+50. They backfilled and compacted trench to spec. they used water truck to prep road for sweeper to clean road. | |
| 07/27/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon laid pipe to station 24+00. Supervisor Steve stated that he will coordinate with his crew to pick up meter box order. They’re about 1-2 days away from completing 8” mainline install. | |
| 07/28/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon laid pipe to station 25+00. They perform sample pressure test before they start tapping services. | |
| 07/29/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon swept road, filled in dips and set up for service taps. they will start installing services tomorrow. | |
| 07/30/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon ran 2 short and two long one inch services. They’re locating mainline, tapping services and boring services under road. | |
| 07/31/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon tapped 3 services and installed FH at station 18+53. this was the last FH that needed to be installed. | |
| 08/07/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon three services. Two long services and one short they also used a water truck for dust Control and swept the road with the sweeper. | |
| 08/10/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon installed 3 services. Two short and one long. meter boxes were set. | |
| 08/11/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon installed two short services and one long service. They they board under the road on a second long service and ran tracer wire. They backfilled trench and will run long service tomorrow. | |
| 08/12/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon tapped and ran two short services and two long services on 36th street. They compacted and laid bury tape. | |
| 08/13/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon tapped three short services and two long services. Tricon pressure tested all services at 200 psi. | |
| 08/14/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon tapped two long copper services and three short services. They backfilled and compacted trench per spec. They pressure tested all services. They completed one temporary patch. | |
| 08/17/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon tapped one short service and backfilled 3 long services. | |
| 08/18/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon installed 2 short and two long services. | |
| 08/19/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon tapped too long and two short services and backfilled. I also placed the order for 123 meters. Tricon will pick up order. | |
| 08/20/2026 | TWPE Daily Field Inspection | In Field Accepted | triCon tapped for short services and too long services on 36th St. They compacted to spec. I informed supervisor L that I placed the meter order and it’s ready to be picked up at the Eastside Stores. | |
| 08/21/2026 | TWPE Daily Field Inspection | In Field Accepted | triCon tap for short services and too long services. The backfilled after compaction. They swept road with sweeper. I am formed supervisor AL that the meter order and material order is ready for pick up at the Eastside Stores location. | |
| 08/24/2026 | TWPE Daily Field Inspection | In Field Accepted | triCon tapped four short services and two long services. All services were pressure tested to 200 psi. They backfilled compacted and used bury tape at each trench. | |
| 08/25/2026 | TWPE Daily Field Inspection | In Field Accepted | triCon tapped four short services and two long services. They backfilled compacted trench and swept the roadway. | |
| 08/26/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon tapped for short services and two long services. The pressure tested all services at 200 psi and backfilled trench in 1 foot lifts. All services had tracer wire and bury tape. They finish their day after sweeping the roadways. | |
| 08/27/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon tapped four short services and three long services. Each service was pressure tested at 200 psi. Each copper service had tracer wire all trenches were backfilled and compacted to spec. | |
| 09/01/2026 | TWPE Daily Field Inspection | In Field Accepted | triCon tapped three short services and pressure tested each one at 200 psi. They set meter boxes and clean up yards that they’ve been working on. | |
| 09/08/2026 | TWPE Daily Field Inspection | In Field Accepted | I spoke with supervisor Al from TriCon to get a weekly update. Today they are replacing the sewer in the alleyway behind Sahara. They have five services left to install on the new main line. They will start on those tomorrow. | |
| 09/10/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon installed 60 feet of 8 inch duct iron pipe on 35th St. to the tie in point on Sahara. That completes the mainline installation. | |
| 09/11/2026 | TWPE Daily Field Inspection | In Field Accepted | TRICON board one long service on 36th St. after today they will have four services left to bore under 36th St. | |
| 09/14/2026 | TWPE Daily Field Inspection | In Field Accepted | triCon laid pipe to the 45 at station 31+05. 92. They installed one long service and backfilled trench. There are two remaining copper services left to be installed on 36th St. | |
| 09/15/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon laid 8 inch duct iron pipe to the tire point on Sahara and 36th St. temporary drain valve assembly was also installed to start filling the line to prepare for the pressure test. | |
| 09/18/2026 | TWPE Daily Field Inspection | In Field Accepted | triCon tapped the final two services on 36th St. and installed air relief valve. They backfilled trenches, compacted trenches, and used bury tape. They will prep for pre-pressure test next week.. | |
| 09/23/2026 | TWPE Daily Field Inspection | In Field Accepted | triCon pothole to Locate gate valve in the alleyway of 36 and Craycroft. They will prep to install 8 inch mainline to the cut and plug station. | |
| 09/24/2026 | TWPE Daily Field Inspection | In Field Accepted | triCon located gate valves in the alleyway of 36th and Craycroft. They located 8 inch existing mainline that reduces down to a 4 inch which will be the cut and plug location Tricon Will start chlorinating new mainline and Will prep for pre-pressure test. | |
| 09/28/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon performed and passed their pre pressure test. We will perform pressure test tomorrow. | |
| 09/29/2026 | TWPE Daily Field Inspection | In Field Accepted | I completed the pressure test for this project. Tricon pumped the line up to 200 psi. The test was from 0700 to 0900. The pressure test passed, there was zero pressure loss within the two hours. I took the high chlorine sample at the drain valve assembly. The chlorine residual was 120+ppm. The high chlorine test was taken at 0915. | |
| 09/30/2026 | TWPE Daily Field Inspection | In Field for Revision | I performed low chlorine test, which was 80 PPM. After TriCon dechlorinated new mainline, I took the bacteriological sample on a riser at the dva. The chlorine residual was .99. I drove the sample to the lab. | |
| 10/01/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon installed an 8 inch tapping sleeve and tapped mainline at station 31+90.93. The pressure tested tapping sleeve at 200 psi for 15 minutes. Pressure test passed. I informed foreman AL that the bacteria logical sample passed and they can move forward with a tie. | |
| 10/02/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon completed tie in. The 10 foot stick of 8 inch DIP had restraints. I visually watched them break off mega lugs. Trench was backfilled and compacted. They also poured thrust block behind tapping sleeve. | |
| 10/05/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon poured thrust block behind the tapping sleeve on Sahara and 35th St. Trench was backfilled to spec. They also completed time on Jefferson and 35th St. | |
| 10/06/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon trenched and located 4 inch cement asbestos mainline in the alleyway of Jefferson and Craycroft. This location will be where they’ll cut and plug mainline. They tapped sacrificial service to see if we could isolate the alleyway. Eastside utility technicians did not complete the mock shut down last week. I informed supervisor Eric to contact the Eastside supervisor and ask them to complete mock shutdown. TriCon will pull postpone plug until the utility technicians verify shut down. | |
| 10/07/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon set 4 meters, installed prv’s and plumbed into customers private plumbing on 36th street. | |
| 10/08/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon replaced two meters on 36th street. | |
| 10/12/2026 | TWPE Daily Field Inspection | In Field Accepted | Tricon replaced two water meters on 35th St. They replumbed to services for customers on 35th St. | |
| TWPE Daily Field Inspection | Scheduled |