Inspection History Details
Inspection Status: In Field Accepted
Inspection History: TWPE Daily Field Inspection
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/06/2026 | TWPE Daily Field Inspection | In Field Accepted | Contractor completed fire line extension at 301+79, lateral extension at 304+44 and Arv at station 306+82 Contractor also grouted old mainline from Desert to Arcadia | |
| 05/07/2026 | TWPE Daily Field Inspection | In Field Accepted | Contractor was preping for tie ins | |
| 05/12/2026 | TWPE Daily Field Inspection | In Field Accepted | Contractor was workin on arv cages and pads. and bac t sample was collected | |
| 05/14/2026 | TWPE Daily Field Inspection | In Field Accepted | contractor prepped for tie ins | |
| 05/15/2026 | TWPE Daily Field Inspection | In Field Accepted | Contractor was prepping for tie ins | |
| 05/18/2026 | TWPE Daily Field Inspection | In Field Accepted | contractor was flushing water line east of Alamo wash i left early due to overnight work and my supervisor EricQuarrel covered me the rest of the day | |
| 05/29/2026 | TWPE Daily Field Inspection | In Field Accepted | contractor completed tie in to fire service at the marque aprtments amd tie in on Sonoita and 5th st | |
| 06/01/2026 | TWPE Daily Field Inspection | In Field Accepted | contractor completed tie in on Mckinley north and Indian Road House. | |
| 06/02/2026 | TWPE Daily Field Inspection | In Field Accepted | Contractor completed tie in at town houses next to Marquee apartments, tie in on sahuara north was not completed due to bad shutdown | |
| 06/03/2026 | TWPE Daily Field Inspection | In Field Accepted | tie in on sahuara north was completed | |
| 06/04/2026 | TWPE Daily Field Inspection | In Field Accepted | Contractor completed tie in at Ruston and 5th st and at rook and 5th st | |
| 06/11/2026 | TWPE Daily Field Inspection | In Field Accepted | contractor has been doing pavement patches and prepping for wilmot and 5th tie in | |
| 06/16/2026 | TWPE Daily Field Inspection | In Field Accepted | Contractor was doing patches and will be working on wilmot tonight | |
| 07/01/2026 | TWPE Daily Field Inspection | In Field Accepted | Contractor was doing punchlist items and wont be back untill next week | |
| 07/13/2026 | TWPE Daily Field Inspection | In Field Accepted | no water work was done | |
| 10/13/2026 | TWPE Daily Field Inspection | In Field Accepted | On 10/12/26 there was a break on existing ca main on Balvedere and 5th st, Miguel Perez was onsite,Hunter put a wrap arounb because they could not shut water off Today 10/13/26 I met with Luis Granillo and his team to try to achieve shutdown but new valves were under pavement, Adam Bishop said he would send a crew out early morning on 10/14/26 to dig those valves out and that way Luis granillo and his crew could. achieve a shutdown. |
|
| 11/06/2026 | TWPE Daily Field Inspection | In Field Accepted | no water work was done | |
| 11/13/2026 | TWPE Daily Field Inspection | In Field Accepted | No water work was done. | |
| TWPE Daily Field Inspection | Scheduled |