Inspection Status: Passed
Inspection History: TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting
| Date |
Description |
Inspector |
Results |
Comments |
| 09/16/2025 |
TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting |
|
Passed |
I met with the contractor on site to discuss the details of the work. Work is to begin immediately and take about two months to complete. Traffic control is a minimum shoulder closure with no impact to the asphalt there is no sidewalks in the area to be impacted |