Inspection Status: Passed
Inspection History: TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting
| Date |
Description |
Inspector |
Results |
Comments |
| 05/05/2025 |
TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting |
|
Passed |
I met with Southwest gas and Arizona pipeline on site where we discussed extending the daily work hours, applying for approval of night, work, and applying for a waiver to use native instead of AB for backfill. Also traffic control concerns about 24hr setups were discussed. |
| 05/30/2025 |
TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting |
|
Passed |
The gas line relocation will be switching to night work starting on Sunday, June 1. Work hours will be Sunday through Thursday 7 PM to 5 AM. Noise exemption has been approved for these times until December if needed. Contractor will also be allowed to use pag 1 for the patches |