Inspection Status: Complete (Recurring)
Inspection History: TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour)
| Date |
Description |
Inspector |
Results |
Comments |
| 04/24/2026 |
TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) |
|
Complete (Recurring) |
first driveway’s curb, radius, and gutter formed, concrete pour scheduled for Monday |
| 04/28/2026 |
TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) |
|
Complete (Recurring) |
curb at radius for Northwest corner of golf links and Wilmot formed |
| 04/30/2026 |
TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) |
|
Complete (Recurring) |
sidewalk and driveway aprons along Wilmont against southbound lane, forming, caps will be needed on all forms, pour scheduled for Monday morning |
| 05/04/2026 |
TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) |
|
Complete (Recurring) |
curbs and sidewalk along Wilmont on East side of job site have begun forming |
| 05/19/2026 |
TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) |
|
Passed |
final section formed and compacted, poured this morning |