Inspection Status: Complete (Recurring)
Inspection History: TRSP - ROW - Concrete - Acceptance (Post-Pour)
| Date |
Description |
Inspector |
Results |
Comments |
| 04/28/2026 |
TRSP - ROW - Concrete - Acceptance (Post-Pour)
|
|
Complete (Recurring) |
curbs, gutters, and radius for sidewalk transition and first driveway all approved |
| 04/30/2026 |
TRSP - ROW - Concrete - Acceptance (Post-Pour)
|
|
Complete (Recurring) |
first driveway, apron, sidewalk between driveways, back stop and curb at Northwest corner of intersection have all been poured |
| 05/04/2026 |
TRSP - ROW - Concrete - Acceptance (Post-Pour)
|
|
Complete (Recurring) |
completed ramp at radius, driveway along Wilmont. Expansion joints in place and grades verified within spec |
| 05/27/2026 |
TRSP - ROW - Concrete - Acceptance (Post-Pour)
|
|
Passed |
last driveway and sidewalk panels poured, verified grades and expansion joints, final power wash scheduled for Monday |