Inspection Status: Passed
Inspection History: TRSP - ROW - Barricade - Setup/Routine
| Date |
Description |
Inspector |
Results |
Comments |
| 05/12/2026 |
TRSP - ROW - Barricade - Setup/Routine |
|
Passed |
No work has begun at the intersection of Trotter sisters and Colossal caves. There are locates painted and right of way has been staked, but no traffic control setup yet. |
| 05/21/2026 |
TRSP - ROW - Barricade - Setup/Routine |
|
Passed |
Site check of the area and no work has begun and no traffic control has been set up. |
| 05/28/2026 |
TRSP - ROW - Barricade - Setup/Routine |
|
Passed |
No work has started on this project yet |
| 06/04/2026 |
TRSP - ROW - Barricade - Setup/Routine |
|
Passed |
No work on site yet. No traffic control on site yet. Some locates have been completed. |
| 06/10/2026 |
TRSP - ROW - Barricade - Setup/Routine |
|
Passed |
No work on site, no traffic control set up. |
| 06/16/2026 |
TRSP - ROW - Barricade - Setup/Routine |
|
Passed |
Work has not started on site yet. |
| 06/22/2026 |
TRSP - ROW - Barricade - Setup/Routine |
|
Passed |
No work on site. After a phone call with the contractor it was determined that this permit would be allowed to expire and a new permit will be acquired several months down the road when the contractor can start the project. |