Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Re-inspection required
Inspection History: TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour)
| Date |
Description |
Inspector |
Results |
Comments |
| 03/16/2026 |
TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) |
|
Re-inspection required |
|
| 03/20/2026 |
TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) |
|
Passed |
All forms were secured braces were upright, and they were rigid replaced panels for like panels on the longer runs. They made their 2% or less pictures of the concrete ticket are in place. I will be doing the post pour on Monday just to verify and do the final |