Inspection Status: Passed
Inspection History: TRSP - PIA - Sidewalk Placement
| Date |
Description |
Inspector |
Results |
Comments |
| 01/08/2026 |
TRSP - PIA - Sidewalk Placement |
|
Passed |
This project is now complete. A final inspection was passed on January 8, 2026. No more inspections are needed on this project. |
| 04/03/2025 |
TRSP - PIA - Sidewalk Placement |
|
Passed |
|
| 04/29/2025 |
TRSP - PIA - Sidewalk Placement |
|
Passed |
|
| 04/29/2025 |
TRSP - PIA - Sidewalk Placement |
|
Passed |
|
| 04/30/2025 |
TRSP - PIA - Sidewalk Placement |
|
Passed |
|
| 05/23/2025 |
TRSP - PIA - Sidewalk Placement |
|
Passed |
Sidewalk and driveway inspection. |
| 07/23/2025 |
TRSP - PIA - Sidewalk Placement |
|
Passed |
see notes |
| 09/12/2025 |
TRSP - PIA - Sidewalk Placement |
|
Passed |
Site Inspection- There has been some small changes to the parking lot area. There has been some grading work done and the surrounding curb and sidewalk are has been cleaned up but there has not been any work to have the existing curb and depressed curb removed. |
| 10/22/2025 |
TRSP - PIA - Sidewalk Placement |
|
Passed |
Today they are pouring about 20 feet of sidewalk and curb. I took pictures of the forms as a pre-pour. I also took pictures of the stairs and ramp leading to the building which were poured a few days earlier. |