Inspection Status: Canceled
Inspection History: TRSP - PIA - AB Placement
| Date |
Description |
Inspector |
Results |
Comments |
| 06/12/2026 |
TRSP - PIA - AB Placement |
|
Canceled |
|
| 10/01/2025 |
TRSP - PIA - AB Placement |
|
Passed |
JudCo LLC is backfilling the trenches on either side of the newly installed transverse grate. They are using roadway AB and bringing it up in lifts of approximately 8-12 inches. They are using a power plate tamper and jumping jack to compact each lift. Also, they are placing the grates into the box and covering it with a meshing in order to comply with SWPPP in the meantime. |
| 12/30/2025 |
TRSP - PIA - AB Placement |
|
Passed |
Austin with the City of Tucson lab took nuclear density test on AB and resulted in 100% compaction and string line did not vary more than .02'. |