Inspection Status: Passed
Inspection History: TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance)
| Date |
Description |
Inspector |
Results |
Comments |
| 01/20/2026 |
TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) |
|
Passed |
All items noted on the punch list have been addressed and corrected. Curb damage repaired, bollards properly secured, no parking signs installed, no outlet signs installed, and stop sign installed. |
| 11/19/2025 |
TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) |
|
Re-inspection required |
All items noted in the walkthrough need to be addressed before the final inspection can be passed. |