Inspection Status: Passed
Inspection History: TRSP - PIA - AB Placement
| Date |
Description |
Inspector |
Results |
Comments |
| 08/27/2025 |
TRSP - PIA - AB Placement |
|
Passed |
Today we did a string line test on the AB and we did not have any deviations of more than 0.02’ I also had density tests ran and both tests passed based on an average proctor of PnP material. A final cross reference will also be applied once the city lab finishes its proctor test. |
| 10/29/2025 |
TRSP - PIA - AB Placement |
|
Passed |
AB placement is complete |