Inspection Status: Re-inspection required
Inspection History: TRSP - ROW - Concrete - Acceptance (Post-Pour)
| Date |
Description |
Inspector |
Results |
Comments |
| 06/11/2025 |
TRSP - ROW - Concrete - Acceptance (Post-Pour)
|
|
Re-inspection required |
Panels have not been replaced and are still out of grade spec, over 3% |
| 07/29/2025 |
TRSP - ROW - Concrete - Acceptance (Post-Pour)
|
|
Passed |
|
| 10/10/2024 |
TRSP - ROW - Concrete - Acceptance (Post-Pour)
|
|
Re-inspection required |
2 panels on north side of driveway out of grade spec, please remove and replace |