Inspection Status: Partial Pass

Inspection History: FCON – OH Piping & Hydro

Date Description Inspector Results Comments
04/08/2025 FCON – OH Piping & Hydro Partial Pass Floors 1 and 2 approved. Check stairwell heads as they have not been installed yet.
05/08/2025 FCON – OH Piping & Hydro Partial Pass North and south canopies approved. check dry heads in entrance canopy.
06/10/2025 FCON – OH Piping & Hydro Partial Pass Inspected the piping on the 2nd floor only ok to cover.
08/11/2025 FCON – OH Piping & Hydro Partial Pass 3RD floor restrooms ok to hard lid. pictures of unburdened sprinkler pipe and head brackets before final approval.
08/25/2025 FCON – OH Piping & Hydro Partial Pass 200 lb on moved branch lines on 3rd floor ok.
01/13/2026 FCON – OH Piping & Hydro Passed