Inspection Status: Partial Pass
Inspection History: FCON – OH Piping & Hydro
| Date |
Description |
Inspector |
Results |
Comments |
| 01/15/2026 |
FCON – OH Piping & Hydro |
|
Partial Pass |
Need heads in IDF room, customer service, main entrance, aquarium, roll up door, and riser room. 4 way braces on risers. |
| 01/13/2026 |
FCON – OH Piping & Hydro |
|
Re-inspection required |
East system not holding pressure. Need to verify pressure test on all second floor heads. West system pressure test approved first floor, missing several hangers. South system O&H first floor approved |
| 03/17/2026 |
FCON – OH Piping & Hydro |
|
Passed |
|