Inspection Status: Partial Pass
Inspection History: FCON – OH Piping & Hydro
| Date |
Description |
Inspector |
Results |
Comments |
| 08/19/2025 |
FCON – OH Piping & Hydro |
|
Partial Pass |
Contractors test cerficitate for overhead piping shall be provided. TFD was unable to inspected all overhead piping and piping supports due to spray in foam having are ready been applied. |
| 08/12/2025 |
FCON – OH Piping & Hydro |
|
Re-inspection required (with fee) |
Missing upright coverage. Nees access to pipes in rooms that have hard lids installed. |
| 08/14/2025 |
FCON – OH Piping & Hydro |
|
Re-inspection required (with fee) |
Second floor not holding pressure. Fifth room fron street on second floor has upright totally covered by insulation. 2 other uprights have insulation debris on them. |
|
FCON – OH Piping & Hydro |
|
Not Ready |
|
| 08/25/2025 |
FCON – OH Piping & Hydro |
|
Passed |
Contractors test certificate for overhead piping was provided. TFD was unable to inspect overhead piping because spray in foam had already been applied. |