Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - ENGR - Site - Assurance Release
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/15/2026 | COT - ENGR - Site - Assurance Release | Not Ready | Water and sewer not complete for requested lots. This and: Drainage that receives from these needs to be complete Common area sidewalk and curbs that effect lots and need to be complete. |
|
| 05/29/2026 | COT - ENGR - Site - Assurance Release | Passed | Partial release for lots 35-37, 40, 41, 43-46, 48-50, 58, 60, 61, 64, 65, 69, 70, 72, 148, 155, 159-164, 167, 173, 176-178. The releases are proportional to the level of completion of the improvements. The Assurances may be partially released. |