Inspection History Details
Inspection Status: Canceled
Inspection History: SITE - Sign Footer/Setback/Excavation Layout/Rebar
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/28/2026 | SITE - Sign Footer/Setback/Excavation Layout/Rebar | Canceled | ||
| 04/14/2026 | SITE - Sign Footer/Setback/Excavation Layout/Rebar | Partial Pass | Reinforcing and dimensions correct, spacing good, ground good. Pipes wrapped. Okay to pour wall footer of pump house. Be advised to call inspections on the building permit when the details are on the building permit. | |
| 04/24/2026 | SITE - Sign Footer/Setback/Excavation Layout/Rebar | Partial Pass | Okay to pour masonry footing for valve enclosure. | |
| 05/12/2026 | SITE - Sign Footer/Setback/Excavation Layout/Rebar | Partial Pass | 13.5' x 9.5' x 12" thick Electrical slab w/ 12" OC #4 BW. Bent bar at edges 6" w/24" splice. Ground in place clamped to mat. Subgrade compacted. Clearances good. Okay to pour. | |
| 09/11/2025 | SITE - Sign Footer/Setback/Excavation Layout/Rebar | Partial Pass | 9/11/25 5 Light pole Footers At S parking lot. 2' dia footers 6' below grade 3' above with form. Reinforcing correct to plan. Ground correct. 1 light pole in middle of lot needs to centered better in form. 1 at SE corner needs dirt removed for correct clearance to rebar. Provide pictures before Pouring. Okay to pour. |
|
| 09/12/2025 | SITE - Sign Footer/Setback/Excavation Layout/Rebar | Partial Pass | 9/12/25 Five light pole footers At North Parking lot. Footers are correct with reinforcing and dimensions. Placement with survey is correct. Ground wire coils will be put in before pouri due to theft considerations. Jake will provide me with photographs of ground wire. Ok to pour light pole footers. |
|
| 09/18/2025 | SITE - Sign Footer/Setback/Excavation Layout/Rebar | Canceled |