Inspection Status: Canceled
Inspection History: ENGR Paving
| Date |
Description |
Inspector |
Results |
Comments |
| 01/15/2025 |
ENGR Paving |
|
Canceled |
|
| 01/16/2025 |
ENGR Paving |
|
Partial Pass |
AB recycled asphalt being used, will relook at all roads when completed. |
| 01/29/2025 |
ENGR Paving |
|
Partial Pass |
Compaction completed on north and west roads meet or exceed specs at 100% compaction/ 01/29/25. |
| 01/30/2025 |
ENGR Paving |
|
Partial Pass |
Compaction test results are over and above what's required. Will return on 01/31/25 for more observations on asphalt placement |
| 01/31/2025 |
ENGR Paving |
|
Partial Pass |
need test results from asphalt and milling will still need to be tested in storage areas. |
| 02/24/2025 |
ENGR Paving |
|
Passed |
|