Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/09/2025 | ENGR Engineering Final | Not Ready | 10/9/25 Short term, bike parking not installed per plan. Striping across driveway to dumpster not installed. ADA parking adjacent to driveway entrance on plan is 6" concrete paving. Slopes at ADA Parking to comply with ADA, striping and signage needs to be per plan. Striped Access aisle connects to sidewalk east of ADA parking space for Access. DG needs to cover disturbed bare earth at Basin South of building. |
|
| 10/31/2025 | ENGR Engineering Final | Partial Pass | 10/31/25 PCCP ADA Parking Space and bike rack pad.. Forms are correct. 6” on 4” AB. AB is loose in areas. Contractor will send pictures of whacker compacting and compacted AB prior to pour. ADA slopes on forms good. Parking space and aisle must be 2% or less. Bike rack form good. Okay to pour both. Request for final when ready. |
|
| 12/11/2025 | ENGR Engineering Final | Passed |