Parcel: 10408051C


Addresses:

4585 N ORACLE RD


Inspection Status: Partial Pass

Inspection History

Permit Number - TD-DEV-1222-00060

Inspection Description -

Inspection Status - Partial Pass

Date Description Inspector Results Comments
09/09/2025 Partial Pass Curb forms on East edge of drive-thru lanes is accurate to plans. Radius curb forms to East of parking area is accurate to plans. Both of these areas call for a pedestrian path; this is not currently accounted for. Planting area curbs in parking area are formed accurate to plans.
Retaining wall along North edge of site: wall dimensions and location are correct, reinforcement is accurate to plans, okay to pour.
09/17/2025 Partial Pass 9/17/25
Contractor has prepped AB for drive-through on east side of building. Subgrade is 95 +%. Curb marks indicated 4” for AB correct. Expansion material in place at curbs. Contractor has installed the number four hooks tied into remesh at thickened edges, and tied it to remesh is placed in the rest of the slab. per plan. Forms look good.
Okay to pour this concrete. pending min 95% compaction tests for AB. Concrete needs to show 4000 psi

Also, the retaining wall along northern edge has under drain and gravel pocket, installed with the geographic in place correctly OK to backfill the retaining wall per plan. Terracon is testing backfill compaction.
09/22/2025 Partial Pass 0/22/25
Vertical curb forms at west end of Drive Through are correct to plan and survey. Okay to pour these curbs. The Subgrade of West section of concrete drive though is not ready for AB yet. Schedule shifted.
Call us back out when ready. Submit compaction results for Subgrade and AB to the portal.
09/24/2025 Partial Pass 9/24/25
Curbs at s side NW entrance correct and okay to pour.
Flat work forms at S entrance correct 4” AB compacted and good to pour. Submit compaction test under site flatwork to portal.

Drivethrough to the north of building Forms are correct. turndown at joint with asphalt correct. Remesh good. Rebar hooks to plan and clearances good. Ok to pour this section of Drive through when pending AB compaction results.
09/26/2025 Partial Pass 9/26/26
Both Drivethrough pours completed within acceptable tolerances.
09/29/2025 Partial Pass 9/29/25
Loading drive to west building. 6” concrete paving. Same turndown reinforcement as Refuse enclosure slab detail at joint where it meets asphalt. Same remesh as drive-through in the middle of driveway and then the heavy duty concrete paving detail reinforcement in the last 20 feet approximately of driveway next to building. Expansion material correct at curbs. Correct to plan. Okay to pour this section.

Request inpsections for remaining flatwork and asphalt paving when AB is ready.
10/01/2025 Partial Pass 10/1/25
Curb Ramps/sidewalk formed at East of building to accessible route across drive-through correct. OK to pour.

F forms for sidewalk running from accessible route to right away sidewalk east of refuse enclosure do not comply. I will check this sidewalk once it is cured to see if it is correct,if it is not correct it will need to be repaired.
10/06/2025 Partial Pass 10/6/25 panels of sidewalk East of Refuse Enclosure where it meets the ROW sidewalk are over 5% running slope. These panels do not comply.
Other ramps and Sidewalk poured comply.
Sidewalk adjacent to loading dock and curb ramp not ready to pour