Inspection History Details
Inspection Status: Partial Pass
Inspection History
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/10/2025 | Partial Pass | Okay to pout ramp at 2721. Reinforcing passed. | ||
| 07/15/2025 | Partial Pass | 7/15/25 New Dock at 2731 E Elvira NE section of site. 5" Thick ramp, #4 @ 18" e.w. Reinforcing is correct. Dimensions correct. Clearances correct. Expansion joint in place at perimeter. Compaction report good. The top of the ramp has 1’ x 2’ thickened edge w/ 90 degree hook with 3 #4 continuous bars at each corner and at end per plan. Reinforcing wrap around forms for Sump pump correct at bottom of slab. Okay to pour. Call us out for light pole footing inspection. |
||
| 07/18/2025 | Partial Pass | 7/18/25 2 Footings for Light poles 25’-1” tall. NE parking area at Footing dimensions and reinforceing is correct to table and detail given by engineer in RFI. Okay to pour footers.. |
||
| 08/08/2025 | Partial Pass | 8/8/25 Curb ramps at east end of 2701, curb ramps at east end of 2731 and side walk at north end of 2731 These poured areas comply. There are a 3 raised sidewalk panels at area of NE end of Building 2731 that need to be repaired because of tripping hazard. There are also areas of broken curbs at the SE end of site that need to be repaired. |
||
| 08/27/2025 | Passed |