Inspection History Details
Inspection Status: Partial Pass
Inspection History: ENGR Paving
Permit Number - TD-DEV-1124-00308
Inspection Description - ENGR Paving
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/05/2025 | ENGR Paving | Partial Pass | Sub-grade is being prepped, compaction results are pending, will need additional inspection to monitor progress prior to AB placement. | |
| 09/08/2025 | ENGR Paving | Partial Pass | Sub-grade is at proper elevation and compaction, okay to place AB. | |
| 09/09/2025 | ENGR Paving | Partial Pass | AB is being worked on West side, progress is slow; not ready to pave, still need to get elevations and compaction | |
| 09/10/2025 | ENGR Paving | Not Ready | AB along West side: 3" depth for AC is not present everywhere, loose AB in some areas. Not ready for asphalt. | |
| 09/11/2025 | ENGR Paving | Partial Pass | AB placement, West and North of concrete valley gutter: compaction, depth, and slope are correct, ready for AC. | |
| 09/12/2025 | ENGR Paving | Partial Pass | Paving progress in Northern most driveline is good. AB along west driveline, east of V-ditch, for the length of the main building: depth and thickness is good, okay for AC pending compaction testing results. |
|
| 09/15/2025 | ENGR Paving | Partial Pass | Paving on the West side progress: 3rd party testing is on site. Slopes, thickness, finish elevations, and compaction are all good. | |
| 09/16/2025 | ENGR Paving | Partial Pass | AB placement, North of main building, remainder: Compaction and elevations are good; okay to pave both sides of building D to the valley gutter on the east side. | |
| 09/17/2025 | ENGR Paving | Partial Pass | AB placement: Elevations, slopes, thickness, and compaction are good, okay to pave along north side of main building and from new metal buildings East to the existing pavement, creating a straight line perpendicular to the main building | |
| 09/18/2025 | ENGR Paving | Partial Pass | Paving North of main building, from metal buildings to existing pavement, 3rd party tester is on site and taking samples. Paving progress is good. | |
| 09/22/2025 | ENGR Paving | Partial Pass | Final portion at NE of site, AB depth, elevation, and compaction are good, okay to pave balance of site. | |
| 09/23/2025 | ENGR Paving | Partial Pass | Final section of paving, NE portion of site: Thickness is good, slopes are good, 3rd party tester is onsite, density is good. |