Permit: TD-DEV-1124-00308

Parcel: 12809006B


Addresses:

1104 S CRAYCROFT RD

Inspection Status: Partial Pass

Inspection History: ENGR Paving

Date Description Inspector Results Comments
09/05/2025 ENGR Paving Partial Pass Sub-grade is being prepped, compaction results are pending, will need additional inspection to monitor progress prior to AB placement.
09/08/2025 ENGR Paving Partial Pass Sub-grade is at proper elevation and compaction, okay to place AB.
09/09/2025 ENGR Paving Partial Pass AB is being worked on West side, progress is slow; not ready to pave, still need to get elevations and compaction
09/10/2025 ENGR Paving Not Ready AB along West side: 3" depth for AC is not present everywhere, loose AB in some areas. Not ready for asphalt.
09/11/2025 ENGR Paving Partial Pass AB placement, West and North of concrete valley gutter: compaction, depth, and slope are correct, ready for AC.
09/12/2025 ENGR Paving Partial Pass Paving progress in Northern most driveline is good.
AB along west driveline, east of V-ditch, for the length of the main building: depth and thickness is good, okay for AC pending compaction testing results.
09/15/2025 ENGR Paving Partial Pass Paving on the West side progress: 3rd party testing is on site. Slopes, thickness, finish elevations, and compaction are all good.
09/16/2025 ENGR Paving Partial Pass AB placement, North of main building, remainder: Compaction and elevations are good; okay to pave both sides of building D to the valley gutter on the east side.
09/17/2025 ENGR Paving Partial Pass AB placement: Elevations, slopes, thickness, and compaction are good, okay to pave along north side of main building and from new metal buildings East to the existing pavement, creating a straight line perpendicular to the main building
09/18/2025 ENGR Paving Partial Pass Paving North of main building, from metal buildings to existing pavement, 3rd party tester is on site and taking samples. Paving progress is good.
09/22/2025 ENGR Paving Partial Pass Final portion at NE of site, AB depth, elevation, and compaction are good, okay to pave balance of site.
09/23/2025 ENGR Paving Partial Pass Final section of paving, NE portion of site: Thickness is good, slopes are good, 3rd party tester is onsite, density is good.