Inspection History Details
Inspection Status: Partial Pass
Inspection History: For trash and recycling enclosures
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/06/2024 | For trash and recycling enclosures | Partial Pass | Chandler 314-629-3524 This slab, footing, and bollards have been poured using a monolithic type of pour. Josh Garcia and myself spoke on this and so no issues in any deviation to structural integrity by doing it this way. Inspection was done by pictures taken by super and a visual inspection the day before the pour. |
|
| 09/17/2024 | For trash and recycling enclosures | Passed | Contractor needs to add number four rebar in the front of the trash closures is missing four of them. Contractor will contact me when they’re in. |