Inspection Status: Complete (Recurring)
Inspection History: COT - ENGR - Stormwater
| Date |
Description |
Inspector |
Results |
Comments |
| 11/09/2023 |
COT - ENGR - Stormwater |
|
Complete (Recurring) |
Everything still in place and looks good at this time. Contractor will call in every two weeks for stormwater inspection. |
| 11/22/2023 |
COT - ENGR - Stormwater |
|
Not Ready |
Contractor has not started installing the storm drains yet. Superintendence not on site is gone for the Thanksgiving holidays. |
| 12/19/2023 |
COT - ENGR - Stormwater |
|
Partial Pass |
Contractors installed 300 lineal feet of 36 inch DHPE. And 260 lineal feet of HDPE. Signed off on set of plans. |