Inspection History Details
Inspection Status: Partial Pass
Inspection History: For trash and recycling enclosures
Permit Number - TD-DEV-1122-00044
Inspection Description - For trash and recycling enclosures
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/30/2025 | For trash and recycling enclosures | Partial Pass | 9/30/25 Footer dimensions Correct. Rebar correct. Send pictures of rebar clear of dirt in areas discussed. Okay to pour footer pending pictures. Request inspections for bollards, slab and Pre grout inspection for 1st lift of RE Wall. |
|
| 10/02/2025 | For trash and recycling enclosures | Not Ready | ||
| 10/14/2025 | For trash and recycling enclosures | Not Ready | 10/14/25 Contractor built wall to the top. Weep holes need to be punched just above footer at slab to ensure grout fills reinforced cells. Mason needs to clean up and repair mortar at 1st course and footer around outside of wall.Do not grout until reinspected. |
|
| 10/15/2025 | For trash and recycling enclosures | Partial Pass | 10/15/25 Okay to grout walls. Send me pictures of grout coming out grout weep holes. Request inspection when bollards holes and mat for floor are ready. Submit compaction report of Subgrade to portal |
|
| 10/20/2025 | For trash and recycling enclosures | Partial Pass | Slab reinforcement and dimensions are good, bollard placement and depths is good. Okay to pour slab with bollards. |