Inspection Status: Re-inspection required
Inspection History: SITE - Stormwater Follow-up
| Date |
Description |
Inspector |
Results |
Comments |
| 01/16/2025 |
SITE - Stormwater Follow-up
|
|
Re-inspection required |
All concrete/stucco mixing areas need to be cleaned up ASAP. |
| 01/23/2025 |
SITE - Stormwater Follow-up
|
|
Complete (Recurring) |
General site maintenance is needed to be done on a regular daily basis. |
| 05/14/2025 |
SITE - Stormwater Follow-up
|
|
Passed |
Work can be started on the notice of termination letter required to close this inspection out. |
| 11/07/2024 |
SITE - Stormwater Follow-up
|
|
Complete (Recurring) |
No Issues. |
| 11/27/2024 |
SITE - Stormwater Follow-up
|
|
Complete (Recurring) |
SWPPP okay. equipment operation should be limited to on-site operation. |
| 12/18/2024 |
SITE - Stormwater Follow-up
|
|
Complete (Recurring) |
By weekly failed miserably. All pictures attached need to be rectified asap or a violation notice will be written. |