Inspection History Details
Inspection Status: Canceled
Inspection History: ENGR Paving
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/14/2025 | ENGR Paving | Canceled | ||
| 05/15/2025 | ENGR Paving | Passed | 05/15/25, Grading completed on the south side of building completed to 3". East side will be observed on the 16th of May before asphalt is installed. 2nd lift is being completed on the west and north sides of building. Observed tack coat and Western Tech on site doing density testing. |
|
| 05/16/2025 | ENGR Paving | Passed | 05/16/25, everything looks good to continue paving this site. |