Inspection History Details
Inspection Status: Partial Pass
Inspection History: For trash and recycling enclosures
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/07/2026 | For trash and recycling enclosures | Partial Pass | Pre grout-Wall is built to the top. Reinforcing correct. Bond beam in place. Contractor will provide pictures of weep holes at bottom course of each filled reinforced cell grouted correctly. Schedule inspection when ready with floor reinforcement and or bollard footers. | |
| 08/25/2026 | For trash and recycling enclosures | Partial Pass | Slab and approach: depth, slope, compaction, and reinforcement are good. Okay to pour slab and approach. Bollard excavations are good. Okay to set bollards. |