Inspection Status: Passed
Inspection History: For trash and recycling enclosures
| Date |
Description |
Inspector |
Results |
Comments |
| 01/22/2026 |
For trash and recycling enclosures |
|
Passed |
Refuse enclosure is complete in accordance with approved plans. |
| 05/15/2025 |
For trash and recycling enclosures |
|
Partial Pass |
05/14/25, footing and bollards pass. |
| 09/03/2025 |
For trash and recycling enclosures |
|
Partial Pass |
Advised to add additional rebar4 at front of wall where gates will be supported; one in the first and second cell. |
| 09/10/2025 |
For trash and recycling enclosures |
|
Partial Pass |
First 2 courses are laid, reinforcement, including bond beam, is correct; okay to grout. |
| 09/11/2025 |
For trash and recycling enclosures |
|
Partial Pass |
Wall block and reinforcement are correct to 4 feet; okay to grout. |
| 09/12/2025 |
For trash and recycling enclosures |
|
Partial Pass |
Trash enclosure and site wall: bond beam is in place, okay to grout and set final course. |
| 09/19/2025 |
For trash and recycling enclosures |
|
Partial Pass |
Trash enclosure slab and approach: reinforcement, sub grade, slope, and thickness are accurate to plans; Okay to pour slab and approach. |