| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/15/2025 | For trash and recycling enclosures | Partial Pass | 05/14/25, footing and bollards pass. | |
| 09/03/2025 | For trash and recycling enclosures | Partial Pass | Advised to add additional rebar4 at front of wall where gates will be supported; one in the first and second cell. | |
| 09/10/2025 | For trash and recycling enclosures | Partial Pass | First 2 courses are laid, reinforcement, including bond beam, is correct; okay to grout. | |
| 09/11/2025 | For trash and recycling enclosures | Partial Pass | Wall block and reinforcement are correct to 4 feet; okay to grout. | |
| 09/12/2025 | For trash and recycling enclosures | Partial Pass | Trash enclosure and site wall: bond beam is in place, okay to grout and set final course. | |
| 09/19/2025 | For trash and recycling enclosures | Partial Pass | Trash enclosure slab and approach: reinforcement, sub grade, slope, and thickness are accurate to plans; Okay to pour slab and approach. |