Inspection Status: Partial Pass
Inspection History: ENGR - Drainage Structures
Permit Number - TD-DEV-1023-00423
Inspection Description - ENGR - Drainage Structures
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/24/2025 | ENGR - Drainage Structures | Partial Pass | 04/24/2025, passed today will be the 2 East basins and drainage structure on the south east corner pipe drain into the rear basin. | |
| 04/25/2025 | ENGR - Drainage Structures | Partial Pass | See checklist items. Outlet Header at catch basin one ready to pour when weir length corrected to 5’. |
|
| 04/30/2025 | ENGR - Drainage Structures | Partial Pass | 04/30/25, 2 footings for the first section of 24" pipe to the south passed. | |
| 05/06/2025 | ENGR - Drainage Structures | Partial Pass | 05/06/25, inlet wall at south end of middle 3 pipe run, good to pour wall. | |
| 05/08/2025 | ENGR - Drainage Structures | Partial Pass | It was found that the NPPO inspection had never been completed holding up all other inspections. Compaction test to date have been received. Final grade inspections need to be done prior to any final concrete or paving is completed. | |
| 07/24/2025 | ENGR - Drainage Structures | Partial Pass | 07/24/25, walls at front drainage pipe are completed. PAG standard 105 rails have been installed. Uprights for pipe are centered at 5'-9" which is good as the rails still meet the 200lb per ft OSHA requirement. | |
| 08/18/2025 | ENGR - Drainage Structures | Canceled |