Parcel: 14122004W


Addresses:

7655 S KOLB RD


Inspection Status: Partial Pass

Inspection History: ENGR - Drainage Structures

Permit Number - TD-DEV-1023-00423

Inspection Description - ENGR - Drainage Structures

Inspection Status - Partial Pass

Date Description Inspector Results Comments
04/24/2025 ENGR - Drainage Structures Partial Pass 04/24/2025, passed today will be the 2 East basins and drainage structure on the south east corner pipe drain into the rear basin.
04/25/2025 ENGR - Drainage Structures Partial Pass See checklist items.
Outlet Header at catch basin one ready to pour when weir length corrected to 5’.
04/30/2025 ENGR - Drainage Structures Partial Pass 04/30/25, 2 footings for the first section of 24" pipe to the south passed.
05/06/2025 ENGR - Drainage Structures Partial Pass 05/06/25, inlet wall at south end of middle 3 pipe run, good to pour wall.
05/08/2025 ENGR - Drainage Structures Partial Pass It was found that the NPPO inspection had never been completed holding up all other inspections. Compaction test to date have been received. Final grade inspections need to be done prior to any final concrete or paving is completed.
07/24/2025 ENGR - Drainage Structures Partial Pass 07/24/25, walls at front drainage pipe are completed. PAG standard 105 rails have been installed. Uprights for pipe are centered at 5'-9" which is good as the rails still meet the 200lb per ft OSHA requirement.
08/18/2025 ENGR - Drainage Structures Canceled