Inspection Status: Complete (Recurring)
Inspection History: SITE - Stormwater Follow-up
| Date |
Description |
Inspector |
Results |
Comments |
| 04/17/2025 |
SITE - Stormwater Follow-up
|
|
Complete (Recurring) |
No concerns at this time |
| 05/08/2025 |
SITE - Stormwater Follow-up
|
|
Complete (Recurring) |
Contractor needs to put wattles around the spoils on the south end of the project |
| 06/05/2025 |
SITE - Stormwater Follow-up
|
|
Complete (Recurring) |
Not concerned at this time everything looks good. Contractor will call in for Stonewater biweekly and two weeks. |
| 07/10/2025 |
SITE - Stormwater Follow-up
|
|
Complete (Recurring) |
No concerning at this time. Continue to call in Biweekly Swppp inspections and after more than .25” rain event. See details for Best management practices. |
| 07/29/2025 |
SITE - Stormwater Follow-up
|
|
Partial Pass |
Contractor needs to add wattles along the fence line on the east side |
| 10/24/2025 |
SITE - Stormwater Follow-up
|
|
Passed |
Site is good overall. Need to set up a designated concrete washout area with proper containment. |