Inspection Status: Partial Pass
Inspection History: COT - BASN - Drainage/Basin - Condition Inspection
| Date |
Description |
Inspector |
Results |
Comments |
| 08/28/2025 |
COT - BASN - Drainage/Basin - Condition Inspection |
|
Partial Pass |
contractor is forming up a weird needs to install the vertical number four bars at every 32 inches per plan good to pour |
| 09/04/2025 |
COT - BASN - Drainage/Basin - Condition Inspection |
|
Partial Pass |
Basin progress is good. Weir is complete and final depth of basin is accurate. Basin floor is being ripped, next step is riprap for the sides. |
| 01/05/2026 |
COT - BASN - Drainage/Basin - Condition Inspection |
|
Passed |
|