Inspection Status: Partial Pass
Inspection History: ENGR Paving
| Date |
Description |
Inspector |
Results |
Comments |
| 10/24/2025 |
ENGR Paving |
|
Partial Pass |
AB Inspection for parking areas not to extend beyond concrete valley gutter: Compaction testing yields 100%, depths are good, grading is accurate for proper drainage. One area along valley gutter on North side in front of clinic doors is measuring short, will need reworked to achieve 2.5 inches of AC, will recheck prior to paving. |
| 10/29/2025 |
ENGR Paving |
|
Partial Pass |
Paving of parking areas on the North and West sides of building: tack coat is applied, asphalt is going in at proper depth and slopes. |
| 11/12/2025 |
ENGR Paving |
|
Partial Pass |
AB is good on remainder of site. Okay to pave. |
| 11/13/2025 |
ENGR Paving |
|
Partial Pass |
Final paving outside of valley gutter and South parking lot: tack coat is good, edges are ready, paving progress is good. |