Inspection Status: Partial Pass
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 04/28/2025 |
ENGR Engineering Final
|
|
Partial Pass |
Contractor has a lot of irrigation lines to to backfill |
| 05/29/2026 |
ENGR Engineering Final
|
|
Partial Pass |
Basketball courts and associated shade structure is complete and safe for public access. 3 of the 6 pickleball courts are complete and safe for public access. Landscaping work is complete. A revised plans reflecting the finished conditions of the site (only 3 pickleball courts) needs to be submitted to PDSD for review and approval of as-built conditions. |
| 06/29/2026 |
ENGR Engineering Final
|
|
Passed |
Park improvements are complete in accordance with approved plans. |
| 11/05/2025 |
ENGR Engineering Final
|
|
Partial Pass |
Revision required to reflect as-built status. |