Inspection Status: Partial Pass
Inspection History: NPPO Pre-Construction
Permit Number - TD-DEV-0823-00382
Inspection Description - NPPO Pre-Construction
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/25/2024 | NPPO Pre-Construction | Partial Pass | Contractor requested an inspection for the footers and rebar for trash enclosure. They’re good for. | |
| 08/01/2024 | NPPO Pre-Construction | Partial Pass | Contractor called in the wrong inspection. He needed to call Lynn for trash, enclosure footer, and rebar. | |
| 08/06/2024 | NPPO Pre-Construction | Partial Pass | Contractor is good to grout at the 4 foot mark | |
| 08/07/2024 | NPPO Pre-Construction | Partial Pass | Contractor called in for the trash enclosure from the 4 foot mark to the 6 foot mark a good to continue laying block | |
| 08/08/2024 | NPPO Pre-Construction | Partial Pass | contractor call in for trash enclosure, pre-grout inspection from the 4 foot mark to the 6 foot good to grout and install Bon beam and cap | |
| 08/21/2024 | NPPO Pre-Construction | Partial Pass | The contractor keeps calling him the wrong inspections. He need the trash enclosure for the floor and the apron, and it’s good to pour. | |
| 12/09/2024 | NPPO Pre-Construction | Passed |