Inspection Status: Partial Pass

Inspection History: ENGR Paving

Permit Number - TD-DEV-0823-00380

Inspection Description - ENGR Paving

Inspection Status - Partial Pass

Date Description Inspector Results Comments
05/19/2025 ENGR Paving Partial Pass Contractor poured concrete for the drive today instead of asphalt.
06/10/2025 ENGR Paving Partial Pass See checklist items for details. Call in striping inspection when ready
07/02/2025 ENGR Paving Partial Pass 7/2/25
Benchmark located top surface of concrete pier on NW light pole. + EL 2471.03. Paving looks like the parking area will drain as intended in the drainage and grading plan. Slopes good including ADA Area.

Contractor will provide me with compaction results in paved areas. Subgrade to be 95% and AB 100% and showing good AC #2 testing results.
The AC on the plans calls for 1 lift. Engineer needs to approve milling and 2 lift change with certified letter for Engineering Final. These conditions will need to be met.

Other notes: missing sidewalk scupper at ROW sidewalk going into WHIA #2.
WHIA #6 is not deep enough.
2 wheel stops 1 east light pole and 1 at ada parking on plans. May be deemed redundant.

Next steps:
Final refuse enclosure
Striping inspection
Landscaping inspection
08/01/2025 ENGR Paving Not Ready Correct asphalt lip at ramp.
08/07/2025 ENGR Paving Passed