Inspection History Details
Inspection Status: Partial Pass
Inspection History: For trash and recycling enclosures
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/22/2026 | For trash and recycling enclosures | Partial Pass | Refuse Enclosure Floor has been poured. It was pre approved for pour by verifying reinforcing is correct by pictures. Layout of Refuse Enclosure is the same as that shown in the DP but it is Detailed in the building plans and is approved by Site Engineering. Wall height and bollards layout differ to TSM section 8.01 but is correct to approved plans. Schedule pre-grout inspection for first lift when wall is 4 feet with correct reinforcing. |
|
| 07/09/2026 | For trash and recycling enclosures | Partial Pass | Refuse enclosure walls, first lift pre-grout: reinforcement is good with #5 bars 24" OC. Okay to grout. | |
| 07/13/2026 | For trash and recycling enclosures | Partial Pass | Second lift pre-grout: 1st lift complete, reinforcement/bond beam is good. Okay to grout. |