Inspection Status: Partial Pass
Inspection History: SITE - Zoning Final
| Date |
Description |
Inspector |
Results |
Comments |
| 03/19/2025 |
SITE - Zoning Final
|
|
Partial Pass |
Contractor is good to pour the sidewalks between Ramada two and three and the sidewalks between three and the and the walking path |
| 03/25/2025 |
SITE - Zoning Final
|
|
Partial Pass |
contractors installing the irrigation lines, but the City Of Tucson park and rec are inspecting it. I’m looking at the new sidewalk that they poured from 2 to3 pass the sidewalk . The bench pads that the contractor poured looks good. Also contractor also is cutting the thicken edge for the walk path. |
| 08/07/2025 |
SITE - Zoning Final
|
|
Passed |
|