Inspection Status: Partial Pass

Inspection History: ENGR Grading Final

Permit Number - TD-DEV-0723-00325

Inspection Description - ENGR Grading Final

Inspection Status - Partial Pass

Date Description Inspector Results Comments
08/07/2025 ENGR Grading Final Partial Pass Trees need to be staked properly with 2 stakes.

I can approve for a level 4 TCO but see above note and the lot used for construction to the east needs to be stabilized by means of hydro seed or some other means of city approved stabilization.
12/02/2025 ENGR Grading Final Partial Pass 12/2/25
Area of unpaved lot to the north side of parking lot and the loading/refuse enclosure area behind building. Grade hubs are in place and good. 3" of AC on 4" ABC. AB needs to be at 95% compaction. String line is good in areas where curb is correct to hubs. Contractor will provide me with pictures of areas where reveal needs to be corrected in a few areas we discussed. Pending compaction results comply with Geo tech recommendations Okay to pave both areas.