Inspection History Details
Inspection Status: Partial Pass
Inspection History: ENGR Paving
Permit Number - TD-DEV-0723-00325
Inspection Description - ENGR Paving
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/05/2025 | ENGR Paving | Partial Pass | Hubs and sub grade have been completed, hubs were visible in several areas. Compaction test will be submitted. An is going in now and will be scheduled for Thursday for compaction and blue top. | |
| 08/08/2025 | ENGR Paving | Partial Pass | 08/08/25, Half lot being completed today 2nd half on the 11th. | |
| 08/12/2025 | ENGR Paving | Partial Pass | Parking lot is completed and meets specs. Entrance still needs to be completed which will keep this inspection from being finished. | |
| 11/25/2025 | ENGR Paving | Partial Pass | Okay to pour pipe encasement apron at entry. | |
| 12/03/2025 | ENGR Paving | Partial Pass | Contractors good to start paving in the back south west corner of the building |