01/06/2026 ENGR Paving Partial Pass contractors removing the asphalt at the south east area where the handicap parking is seven parking stalls because it’s noncompliant
Contractor also is removing the sidewalk in the same area because it’s a noncompliant
Contractor removing concrete in the patio area that’s noncompliant
Contractors removing asphalt up against the bollards on the west side by the trash enclosure the walkway through there is noncompliant
01/07/2026 ENGR Paving Partial Pass contractor pour the sidewalks area in front of the building
Continuing to remove asphalt where the handicap parking was. Will probably start paving on Friday because it’s starting to rain today.
ENGR Paving Scheduled
08/05/2025 ENGR Paving Partial Pass Hubs and sub grade have been completed, hubs were visible in several areas. Compaction test will be submitted. An is going in now and will be scheduled for Thursday for compaction and blue top.
08/08/2025 ENGR Paving Partial Pass 08/08/25, Half lot being completed today 2nd half on the 11th.
08/12/2025 ENGR Paving Partial Pass Parking lot is completed and meets specs. Entrance still needs to be completed which will keep this inspection from being finished.
11/25/2025 ENGR Paving Partial Pass Okay to pour pipe encasement apron at entry.
12/03/2025 ENGR Paving Partial Pass Contractors good to start paving in the back south west corner of the building
12/31/2025 ENGR Paving Partial Pass Contractor needs to remove the majority of the handicap parking up against the building because of the slopes are noncompliant