Permit: TD-DEV-0623-00286

Parcel: 133100210


Addresses:

8535 E SPEEDWAY BL

Inspection Status: Complete (Recurring)

Inspection History: COT - ENGR - Stormwater

Date Description Inspector Results Comments
02/06/2024 COT - ENGR - Stormwater Complete (Recurring) track out pad installed per plan.

wattles on south and west sides not properly installed/maintained.

wattles on north and south sides of track out pad not properly installed.

stormwater 3rd party vendor not reading inspector notes and stating no problems with controls in written reports.

stormwater pipe is plastic as per plan.

stormwater pipe backfill was not complete at time of inspection (south side).
02/21/2024 COT - ENGR - Stormwater Complete (Recurring) catchbasin #1 formed and ready for concrete.
02/26/2024 COT - ENGR - Stormwater Complete (Recurring) observed east side HDPE pipe backfill 12” coverage
02/29/2024 COT - ENGR - Stormwater Complete (Recurring) installing east drainageHDPE pipe to north drainage basin, plus inlet structure #3, sand backfill was at least 12” above pipe.
03/04/2024 COT - ENGR - Stormwater Complete (Recurring) no activity. Inlet #3 poured and needs framing removed.
04/18/2024 COT - ENGR - Stormwater Partial Pass footer and wall rebar, no issues at this time
06/17/2024 COT - ENGR - Stormwater Partial Pass No concerns at this time they’re not ready for catch basins or landscaping just yet